July 7, 2003

Tonight's work finally made a change in the appearance of the forms I sent at the beginning. I installed a form that seperates the first and second pour of concrete. It will be removed before the second pour and will act to hold the rebar in place for the first pour. I hauled more rock to fill in around the new form. I will not backfill the second pour area until the first half is poured since the cement truck will need to back in this area to reach the back.